November 2004 - Connector to westbound 91 under construction (RXSQ)

Contract dispute halts work on ‘Malfunction Junction’

After years of waiting for reconstruction of the 60/91/215 freeway interchange in downtown Riverside — AKA “Malfunction Junction” — drivers will have to wait even longer as a recent contract dispute between Caltrans and the primary contractor (Washington-Obayashi) has halted work on the $318 million project.

After a year of commitment, the contractor on the region’s most ambitious transportation project has halted most work and is threatening to pull out of the job permanently, citing what it called an overwhelming number of design changes demanded by Caltrans. The withdrawal leaves behind unfinished bridges and aborted upgrades at the notoriously gridlocked intersection.

Riverside Press-Enterprise – February 20, 2005

The dispute centers around the use by Caltrans of what is known as “design sequencing,” a process by which the final phases of a project are designed while construction begins on earlier phases. Such a process is meant to both save money and speed up the overall completion by beginning construction earlier in the design process. However, it can also increase the likelihood of design changes during construction as plans become finalized.

Although budgeted with a 10% contingency fund, Caltrans says the requested changes, which Washington-Obayashi says is now forcing them to seriously consider pulling out of the entire project, have not gone above and beyond what was expected in such a process.

Moreover, with other bids ranging from $198 million to $208 million, some officials have even hinted that Washington-Obayashi — at $186 million — may have significantly underbid their portion of the project.

If a permanent pull-out by Washington-Obayashi does come to pass, Caltrans says the remainder of the 4-year project would still be attractive enough to another bidder and may only stall the project for as little as 6 months — offering some solace for the 330,000 drivers who trudge through the snarled interchange each day.

Related

  • Riverside Press-Enterprise – Ground to a halt (Feb. 20) | ‘It just sucks you in, holds you under’ (Feb. 20)

Previous

Sources: Riverside Press-Enterprise (PE-20050220); NOTE: Published dates for some online versions of newspaper articles cited may not match their archival source date.

2024 PAGE UPDATE: Added newspaper citation/insert; removed outdated links to newspaper articles.

Similar Posts

  • |

    Is streetcar service in Riverside’s ‘reconnected’ future?

    A special and unique appearance of a light rail car in downtown Riverside on Thursday gave residents a chance to view the possible future of transportation in Riverside. It also brought back the idea of Southern California’s once grand, Pacific Electric streetcar system, which formerly ran lines down Main, Market, Seventh (Mission Inn) and Magnolia…

  • UCR moves up in rankings

    Rising seven spots from last year, the University of California at Riverside continues its upward climb in the latest rankings of the nation’s top higher-learning institutions as compiled by Washington Monthly. The #15 ranking is another indication that UCR — and the UC system in general — remains one of the top public educational institutions…

  • 3.8 million and counting

    According to the latest population estimates just released by the U.S. Census Bureau, Inland Southern California once again led the state in population growth as both Riverside and San Bernardino counties ranked in the top 5 in the number of new residents. Together, the two counties added nearly 150,000 residents between July 2003 and July…

  • | |

    Two iconic downtown Riverside buildings turn 50

    When gazing upon the skyline of downtown Riverside from atop Mount Rubidoux, two office buildings tend to stand out: Riverside County Administrative Center (the “glass box” and city’s tallest building) and Riverside City Hall (seven-story, chocolate brown building with low-slung arches). Both buildings were designed by the Riverside-based architectural firm founded by Herman Otto Ruhnau….

  • High-end homes

    With housing demand — and prices — shooting through the roof, it’s no surprise that a recent wave of high-end housing is taking root within the arroyos and valleys of Inland Southern California. The 580-acre Vellano project in Chino Hills will offer semi-custom homes priced between $900,000 and $1.5 million as well as 50 lots…

3 Comments

Leave a Reply

Your email address will not be published. Required fields are marked *